Two feeds and one technician

A trading system takes prices from two redundant data feeds and keeps working as long as at least one feed is up. Each feed, while up, fails after an exponential time with mean 11 day, independently of the other. There is one technician: whenever a feed is down she repairs it, which takes an exponential time with mean 88 hours. The system goes dark the first time both feeds are down at once. Starting with both feeds up, what is the expected time in days until the system goes dark?

Show hints (2)+
  1. In each state, add the mean time until the next event, then average over which event happens first.
  2. With one feed down, what is the chance the repair finishes before the other feed fails?

Answer

Reveal answer →

3 (± 0.01)