Valid orders for a small build
Seven build tasks A-G have dependencies (X→Y means X must finish before Y starts):
A→B, B→C, D→E, E→F, A→E, C→G, F→G.
Tasks run one at a time. How many valid orders (topological sorts) are there?
Show hints (2)+
- Is there a task that must always come last?
- Two chains of 3 interleave in ways; which of those break A→E?
Answer
Reveal answer →Final answer
16